Operations 05

Installation & Deliverables

What is on site, what is blocked, and who owes the next thing?

No data10 measures specified

What is blocking this surface

The gates are specified three times over and implemented as paper. The defect register with the closest schema ships as ruled empty rows with a print button as its only control.

ConsequenceThe final payment tranche is released on signed snag-clear. The list that unlocks the last of the money is currently a printed sheet.

Already exists — do not rebuild
The staff job board is the master install schedule and runs, with actuals arriving from site. Extend it; do not duplicate it.

Measures specified

none computable — no data
MeasureState
Projects by gateNo data
Site-readiness pass rateNo data
On-time installation startNo data
On-time completionNo data
First-pass QCNo data
NCRs per projectNo data
Average snag-clear daysNo data
Rework costNo data
Installation-caused margin leakageNo data
Damage during installationNo data

Row shapeEvery project row shows: next deliverable · due date · owner · blocker · dependency · customer approval · current drawing or specification version.